Skip to main content

White Bridge repair scheme progressing towards completion soon

White Bridge - Copy

The major scheme to repair Berw Road bridge in Pontypridd has entered its final stages. Upcoming activity to install signs, railings and street lighting, along with nearby resurfacing work, will enable the bridge to fully re-open. 

The Listed structure, known as White Bridge, was severely damaged by Storm Dennis – and the Council has worked very closely with Cadw on the development and delivery of a complex restoration scheme. It has included several hundred individual concrete and structural steelwork repairs, bridge deck waterproofing and repairs, and replacing the highway drainage system.

This latest update confirms that the bridge is currently on course to reopen to two-way traffic and pedestrians by the end of July 2024.

Since all structural repairs were completed on the final section of the bridge in the New Year, focus has moved onto concrete repairs, waterproofing the bridge deck, and constructing a replacement highway drainage system. Good progress on these elements has enabled the scheme to reach its final stages.

Last week (July 1-7), parapet painting was completed, along with the installation of the plates for an illuminated handrail. The Council’s contractor also began removing its facilities away from the site, including larger cabins.

This week (July 8-14), the contractor will commence the installation of street lighting, complete the surfacing and the contractor’s demobilisation from the site will also be completed.

In the fortnight ahead (until late July 2024), final works will include completing the street lighting, installing signage, and repairing railings on the Berw Road side of the bridge. Resurfacing at The Parade will also be undertaken – and upon completion White Bridge can reopen to two-way traffic and pedestrians.

While this will represent the permanent re-opening of the bridge, the Council is giving notice that further traffic management will be needed later this year. This will be essential to repair the ornamental railings located on the bridge.

Councillor Andrew Morgan OBE, Leader of Rhondda Cynon Taf Council and Cabinet Member for Infrastructure and Investment, said: “It’s fantastic news that the ongoing, major White Bridge repair scheme will shortly be reaching its conclusion. Today’s progress report has confirmed that the contractor’s focus is turning to the final elements of the scheme, which will enable the bridge to open to traffic and pedestrians by the end of July 2024.

“Surfacing on the bridge and reinstatement of the footways is nearing completion. The upcoming work will also tie into a nearby resurfacing scheme at The Parade, which is being completed to coincide with the final element of the White Bridge scheme to avoid further disruption in the future.

“The exact arrangements for reopening White Bridge will be communicated by the Council in the weeks ahead, once they have been finalised. It’s pleasing that the scheme is due to be completed ahead of the National Eisteddfod in Pontypridd from August 3-10, which will help with local traffic arrangements.

“As the scheme is nearing completion, I’d like to again thank local residents for your considerable cooperation throughout. This has been a very complex restoration scheme that has caused unavoidable disruption over an extended time period – and the community’s patience has been much appreciated.”

Posted on 12/07/2024